Situation at the Port of Nhava Sheva - final update 26 August, 2010
This is to inform all concerned parties that on 26 August, 2010, the twentieth after the collision between MSC CHITRA and KHALIJIA 3, port operations are back to normal.
Below are the details of services and vessels that will affect OOCL customers:
| 1) CPX |
OOCL CHARLESTON 007 |
- Vessel sailed from NHV on 26.08.10 at 1145 hrs after completing her full operation |
| |
|
|
| 2) CIX |
OOCL JAKARTA 002 |
- Due to the delay caused by an MSC Vessel, berthing of OJK is not confirmed at NHV. We are working closely with terminal for berthing* |
| |
|
|
| 3) IEX |
CMA CGM PUGET 015 |
- Vessel arriving NHV on 29.08.10 |
*One of the MSC vessels at NSICT is delayed. The terminal has confirmed that she will sail by today. This has impacted the complete planning of NSICT and shall affect our vessel, M.V. OOCL JAKARTA on its Friday window. The delay is now 48 hours at NSICT. The APL vessel at CB04 APL SOKHNA has also been delayed by 24 hours.